2G Ethanol Commercial project
100 KLPD production of 2G Ethanol
Status as on 29.02.2024
Company:
Indian Oil Corporation Ltd.
Project:
2G Ethanol Commercial project
Plan Location:
Bohali, Panipat, Haryana
Technology Licensor:
Praj Industries Ltd.
Ethanol Production Capacity (KLPD):
100
Feed Stock :
Rice Straw
Biomass Processing Capacity (MTPD):
425.7
Schedule for Milestones Completion (MoA Milestones)
|
|
Erection and Installation of Proprietary Equipment | Sep- 2021 | Jan 2022 | Jan-2022 |
Mechanical Completion | May- 2022 | Mar 2023 | Jul-2023 |
25% of Annual Production Capacity | Dec- 2022 | Feb 2025 | |
75% of Annual Production Capacity | Mar- 2023 | Feb 2026 | |
FA Release plan (all figures in Rs Crore)
|
FA Release plan | Original | 37.5 | 112.5 | 0 |
Revised | 37.5 | 37.5 | 0 |
Actual FA release | 37.5 | 37.5 | 0 |
Schedule Performance
|
Physical Progress | 50 | |
Construction Progress | | |
Manufacturing & Delivery Progress | | |
Financial Progress | | - |
Cumulative Actual | Commitment | |
Expenditure | |
FY 2021-22 | Outlay BE/RE | |
Expenditure | |