2G Ethanol Commercial project

100 KLPD production of 2G Ethanol 


Status as on 29.02.2024

Company:
Indian Oil Corporation Ltd.
Project:
2G Ethanol Commercial project
Plan Location:
Bohali, Panipat, Haryana
Technology Licensor:
Praj Industries Ltd.
Ethanol Production Capacity (KLPD):
100
Feed Stock                                          :
Rice Straw
Biomass Processing Capacity (MTPD):
425.7


Schedule for Milestones Completion (MoA Milestones)

MilestonesScheduleActual Completion
OriginalRevisedDate
Erection and Installation of Proprietary Equipment

Sep- 2021

Jan 2022

Jan-2022
Mechanical Completion

May- 2022

Mar 2023

Jul-2023
25% of Annual Production Capacity

Dec- 2022

Feb 2025

 
75% of Annual Production Capacity

Mar- 2023

Feb 2026 

 


FA Release plan (all figures in Rs Crore)

--2021-20222022-20232023-2024
FA Release planOriginal37.5112.50
Revised37.537.50
Actual FA release37.537.50


Schedule Performance 

TitleScheduleActual
Physical Progress50 
Construction Progress  
Manufacturing & Delivery Progress  
Financial Progress -
Cumulative ActualCommitment 
Expenditure 
FY 2021-22Outlay BE/RE 
Expenditure 