2G Ethanol Commercial project
100 KLPD production of 2G Ethanol
Status as on 29.02.2024
Company:
Hindustan Petroleum Corporation Ltd.
Project:
2G Ethanol Commercial project
Plan Location:
Talwandi Sabo, Bathinda, Punjab
Technology Licensor:
Praj Industries Ltd.
Ethanol Production Capacity (KLPD):
100
Feed Stock :
Rice Straw
Biomass Processing Capacity (MTPD):
420
Schedule for Milestones Completion (MoA Milestones)
Milestones | Schedule | Actual Completion |
---|
Original | Revised | Date |
---|
Erection and Installation of Proprietary Equipment | Feb- 2022 | Jul- 2022 | Jul-2022 |
---|
Mechanical Completion | Nov- 2022 | Aug- 2024 | Mar- 2024 |
25% of Annual Production Capacity | Mar- 2023 | Aug- 2025 | - |
75% of Annual Production Capacity | Dec- 2023 | Aug- 2026 | - |
|
FA Release plan (all figures in Rs Crore)
- | - | 2021-2022 | 2022-2023 | 2023-2024 |
---|
FA Release plan | Original | 37.5 | 75 | 37.5 |
Revised | - | 37.5 | - |
Actual FA release | - | 37.5 | - |
Schedule Performance
Title | Schedule | Actual |
---|
Physical Progress | | |
Construction Progress | | |
Manufacturing & Delivery Progress | | |
Financial Progress | | |
Cumulative Actual | Commitment | |
Expenditure | |
FY 2021-22 | Outlay BE/RE | |
Expenditure | |